Sibiu-Pitesti motorway, section 1, Sibiu-Boița
Company | S.C. PORR Construct S.R.L. |
Principal | National Company for the Administration of Road Infrastructure |
Location | Sibiu - Romania |
Type | Road construction |
Runtime | 04.2019 - 05.2023 |
Securing connectivity.
The Sibiu-Pitești Motorway is an integral part of the Trans-European Transport Network, in short TEN-T, more precisely of the Rhine-Danube Corridor, which crosses the Romanian territory from west to east in the direction Nădlac-Arad-Timișoara-Lugoj-Deva-Sibiu-Pitești-Bucharest-Constanța.
At the beginning of this project, the according Sibiu-Pitești Motorway sector was divided into five sections. For Section 1, with a length of 13.170km, the motorway route starts in the area of Șelimbăr, at the junction with Sibiu Bypass. The motorway route crosses the localities of Șelimbăr and Tălmaciu to the southwest of the DN7 up to the Boița area. There a road junction is to be built, ensuring the connectivity of Sibiu-Pitești Motorway with the DN7 for the future.
Main activities.
- Motorway with two lanes in each direction, hard surface width of 26m along the length of 13.170km
- Two road junctions: Sibiu and Boița
- Two service spaces of type S1 at km 8.200 left, km 8.200 right
- A maintenance and coordination centre in the area of the Boița road junction
- A viaduct with 10 spans at km 10.470, at a length of 414.70m
- A viaduct with 8 spans at km 12.375, at a length of 651.40m
- 27 bridges and passages
- 27 culverts
Road works. | Bridge works, total length: 2,094.25m. | ||
Excavation | 1,912,877m³ | Drilled piles | 15,086m |
Fill | 1.330,932m³ | Concrete | 88,624m³ |
Subgrade layer | 216,423m³ | Reinforcement | 11,977t |
Ballast | 162,140m³ | Prefabricated beams | 393pcs. |
Stabilized ballast | 66,943m³ | Formwork | 122,082m² |
Asphalt mixture | 209,389t |